Posted in: News
Wim Boydens introduced the workshop as Chair and addressed both the state of the art of hybridGEOTABS technology and the future potentials in terms of results' exploitation.
Presentations included topics on Heat pump design and markets, model predictive control, geothermal applications, design and value of hybridGEOTABS buildings.
Our total number of attendees reached 11 external stakeholders, as well as the six speakers presenting the project, 17 total.
This encouraged a lively and discursive open debate following the talks, based on:
The questions and answers have been added as FAQs providing more information on hybridGEOTABS buildings and the motivations of the project.
Lukas Ferkl (Energoklastr): The optimisations produced by MPC do not depend on the starting point of characterisation but, as Anke Uytterhoeven (KU Leuven) added, the important goal is to take into account the most amount of predictions and anticipations that are involved in the technology development process.
Lukas Ferkl: This is not a needed indicator, but if it is taken as a parameter it will for sure improve the quality of the predictions because the more information is gathered, the best outcomes are reached when it comes to behavioral anticipations.
Lukas Ferkl: Considering family households lots of data are needed, so, at the moment, public buildings such as school and offices are more predictable in terms of energy behaviours because we already know what are the daily activities involved and how they are interconnected to the building itself.
Anke Uytterhoeven: The development of an MPC controller has got better potential rather than giving to individual's freedom to react to the behaviour of the system.
Lukas Ferkl: There are already examples where the electricity network can save costs making households pay just for the energy consumed from the city grid and not pay for the one produced locally. SEB attendee: Sadly, in Austria this is still not possible.
Wim Boydens: The envelope has a system of pipes that is being heated while the MPC can predict the temperature overnight or during the day for the next 6-8 hours.
Wim Boydens: TABS controls set a profile-controlled temperature that does not change among different zones.
Gert Dewandeleer (Nathan): The key point is to train the installers to a high level of expertise. Wim Boydens added that on the control side as well there is still lots of work to do and it constitutes a big challenge. SEB attendee agreed that on the heat pump installation side, the training is a very important issue and in her company there is already a program developed for trainings/installations.
Anne Caminade (Lemon Consult): Usually a tendering document is based on a collection of data that is used to develop the project, letting the installers be aware on how to work with the systems involved. Also, students can be included in training programmes as well, and in any case there is always a quality assurance assessment for every project launched. Wim Boydens noted there is also the plan to start a training body that is not focused just on the heating pumps installation, but on their integrations with other systems. Gert Dewandeleer added that from the manufacturers side there is already the possibility for the installer to actually visit the installation site checking whether or not the heat pump was installed correctly.
Wim Boydens: At the moment the project outputs are being tested on 4No. case study buildings where elderly houses and schools are included.
SEB attendee: Company customers are willing to follow a new approach but then, on a practical side, we can see that there is a lack of courage when it comes for example to public buildings (using an example about a public building in Austria that could have been a good starting point to invest in new energy systems, but it then resulted in a weak designed construction). Another example in Salzburg, was how inhabitants are slowly moving outside the city, in the suburbs, to build single family houses and the key problem is that construction companies still don’t know that they can already use new technologies. In addition to this, the company already has a team working on building services, and the Austrian regulation schemes require different indicators combinations not only focused on energy efficiency, but also on primary energy consumption.
Lukas Ferkl: An example related to a district in Netherlands shows good results and it is working fine even if the starting investment was high. Plus there is also another call within the H2020 projects to be exploited concerning energy districts.
Wim Boydens: There are already tests on the ceiling effects and the face-change materials. Anne Caminade then gave a short introduction to face-change materials.
Wim Boydens: This also happens in Luxembourg, where there is no possibility to drill as there is an underground layer of drinkable water. In countries where there are no rules on geodetic regulations it is better to not rush the technology.
The discussion ended with Wim Boydens addressing the potentials of hybridGEOTABS and how nowadays people are of course attracted by new technology advantages, but in order to have a market uptake it also needed a life-cycle analysis otherwise, and SEBs agreed, companies will not invest on them.
The feedback about the whole WSED event was excellent – more than 660 experts from 60 countries participated in the 3 conference days of the World Sustainable Energy Days.
Wim Boydens, EHPA/Boydens Engineering, Belgium
Anke Uytterhoeven, KULeuven, Belgium
Lukas Ferkl, Energoklastr, Czech Republic
Hector Cano, Geoter, Spain
Gert Dewandeleer, Nathan, Belgium-The Netherlands
Anne Caminade, Lemon Consult, Switzerland
Suleyman Dag, Uponor, Finland
The European Energy Efficiency Conference 2020 will take place from 4-6 March. The deadline for the Call for Papers is 10 October 2019. Further information will be published in the coming weeks at www.wsed.at